The Louisiana Public Service Commission is approving several Entergy projects that are supposed to ramp up power generation ...
The approval would allow the unit to construct three new combined cycle combustion turbine generation facilities, with two ...
The Louisiana Public Service Commission, or LPSC, has approved a landmark agreement that paves the way for Entergy Louisiana ...
State utility regulators approved a plan Wednesday to install three natural-gas fueled power plants for the tech company Meta, which needs the electricity for a massive data center it’s building in ...
The Louisiana Public Service Commission voted 4-1 to approve Entergy’s plan to build three natural gas power plants for Meta’s $800M data center in Richland Parish ...
When Meta selected a site in Louisiana for its largest data center to date, it signed a deal with Entergy to power the site ...
If the Public Service Commission approves the plan, Entergy will have the greenlight to build three new gas plants to power ...
Louisianas Public Service Commission approved Entergys proposal to build three combined-cycle gas turbines and supporting transmission infrastructure to power Metas $10 billion AI data center in ...
The Louisiana Public Service Commission gave Entergy the green light to construct three power plants in preparation for the ...
The Louisiana Public Service Commission (LPSC) has given the go-ahead for the installation of three natural gas turbines set to power Meta’s planned 2GW data center in Richland Parish, Louisiana.
Meta’s data center will need about three times the amount of electricity that New Orleans uses in a year and increase Entergy ...
The facility is set to require more than double the energy needed to power the entire city of New Orleans during peak summer heat.